Start with a site survey, then order internet and arrange your phone numbers straight away, because the carrier is the longest lead item. Cabling, Wi-Fi, phones, CCTV, meeting-room AV and a data plan follow in that order, ending with a rehearsed cutover weekend and a snagging list. Order matters more than speed.
Most office moves that go badly in Dubai fail on sequence, not technical work: the internet was ordered after the fit-out started, or nobody checked whether the numbers could follow the business. Work through these phases in order, each with a named owner.
The survey decides where the comms room goes, and the comms room decides almost everything else. Walk the space with your IT partner and fit-out contractor while moving a wall is still free.
Record the outcome as a short design brief: outlets per area, access point and camera positions, what moves and what is bought new. Our IT infrastructure team starts every relocation from this document.
The carrier is the longest lead item, so order it the week the lease is agreed. Business fibre comes from e& (formerly Etisalat) or du, depending on who serves the building. Neither publishes a fixed installation lead time, so ask for a committed date and chase it weekly. If your current carrier matters to you, check which one serves the building before you sign the lease.
Decide on your numbers at the same time. TDRA launched fixed number portability in 2021, so a business can keep a landline while changing carrier, provided bills are paid and the number is connected. e& says a switch to its service typically takes 3 to 10 business days, with the new service activated before the old one ends.
The constraint: e& states you cannot keep a fixed number when you move between emirates, because each has its own prefix, 02 for Abu Dhabi and 04 for Dubai. For a move within Dubai, confirm in writing that each number will follow you, and on which date.
List everything first: every DID, the main number, any 800 number, fax, alarm and lift lines, and static IP addresses that firewalls, VPNs or suppliers depend on.
Cabling is what you live with longest, so specify it rather than accept the fit-out contractor's default: Category 6 or 6A copper to each outlet, access point and camera, and fibre for the backbone to distant floors or racks.
Our structured cabling service covers design, installation, labelling and certification as one package.
Glass meeting rooms, concrete cores and neighbours' networks change how signal behaves, and a floor plan shows none of them. Cisco Meraki strongly encourages site surveys before and after deployment, and for voice designs to a cell edge of around -67 dBm with a signal-to-noise ratio of 25 dB or more.
If staff take calls on laptops, Microsoft recommends QoS or WMM, careful band planning and non-overlapping channels for Wi-Fi carrying Teams calls, and offers a Network Planner to estimate bandwidth per site. A predictive design places the access points; a survey after installation proves they work, and it should be repeated once the office is furnished and occupied.
An on-premise PBX has to be shut down, moved, reconnected to the carrier and tested, and your numbers are down for as long as that takes. Moving to the cloud first turns the office change into plugging in phones. Wildix, for which NETON is a certified Gold Partner, offers a cloud PBX with no on-site hardware required and apps for iOS and Android, so users can take calls on laptops and mobiles while desks are moved. That takes most of the risk out of the cutover weekend, and it separates your numbers from the building for the next move too.
Either way, test inbound to every number, outbound from every handset, hunt groups, the auto attendant, voicemail, call recording and any CRM integration your sales team relies on. Our guide to choosing a business phone system covers both options.
Law No. 12 of 2016 established the Security Industry Regulatory Agency (SIRA) and defines selling and installing security systems as a security service. Article 17 states that no one may provide security services in the emirate without a licence, and SIRA publishes a directory of security system provider companies.
Detailed technical requirements sit in the implementing bylaw, with stricter rules for sectors such as banks, hotels, malls and hospitals. Ask your provider which apply before the camera layout is fixed, and check the building's rules for shared areas. Each camera and reader needs a cable run, so plan them with the cabling. See our CCTV and security systems page.
Microsoft's Teams Rooms guidance starts with an inventory of each room's size, layout and purpose, and says to check acoustics, noisy air conditioning, sightlines and power before choosing equipment. Each room device also needs its own Teams Rooms licence. Decide per room whether you need a screen for presenting only or a full video-conferencing system with camera, microphones and speakers, then put cable runs, power and wall reinforcement into the fit-out drawings so nothing is surface-mounted afterwards. See our audio-video for meeting rooms page.
The move is the riskiest day your data will have all year. Hardware gets dropped, disks that have run for years fail on their first restart, and nobody wants to discover a backup problem with the server in a van.
The cutover weekend should hold no decisions, only steps. Write the plan as a numbered script with times, owners and a test for each step, and walk through it with everyone involved before the day.
Keep someone at the old site until the new one is confirmed working, and keep the old internet service live until the new one has carried a full working week.
Walk every floor in the first days with a punch list: dead outlets, weak Wi-Fi, unlabelled cables, poor camera angles, screens that will not share. Close each item with the responsible installer, collect the handover pack (test results, diagrams, survey reports, credentials, warranties), and store admin credentials in your password vault, not on a sticky note in the comms room. Only then cancel the old site's services, in writing, after confirming every number has moved.
Free zones and individual towers add their own layers: contractor permits, work-hour limits, and rules on risers and rooftop equipment. None of these are hard, but each adds days if you discover it late.
NETON delivers every workstream in this checklist for projects in the UAE, from cabling and phones to CCTV, AV and the cutover itself. Send us your new address and target move date, and we will help you put the sequence in order.
| When | Task | Who |
|---|---|---|
| As soon as the lease is agreed | Site survey: comms room, power, cooling, risers, building contractor rules | IT lead, IT partner, building management |
| Immediately after the survey | Order business fibre at the new address and confirm how each number will move | IT lead with e& or du account manager |
| During fit-out design | Cabling design: outlet count, Cat 6 or Cat 6A, fibre backbone, labelling scheme | IT partner with the fit-out contractor |
| During fit-out design | CCTV and access control design submitted through a SIRA-licensed provider | Security provider, landlord |
| After ceilings and partitions are in | Cabling installed, labelled and certified; Wi-Fi survey and access point placement | Cabling installer, IT partner |
| Once the fibre is live | Phone system configured, numbers tested inbound and outbound, meeting-room AV installed | Telephony partner, AV installer |
| The week before the move | Full backup verified, user data synced to the cloud, rollback plan written | IT lead, IT partner |
| Cutover weekend | Servers and network moved, services switched, test script run end to end | IT partner, with a business sign-off |
| First weeks in the new office | Snagging walk, punch list closed, old site services cancelled | IT lead, IT partner, carrier |
Usually yes, if you stay in the same emirate, but it depends on your carrier and your new building, so confirm it in writing before you sign the order. e& states plainly that you cannot keep a fixed number when moving from one emirate to another, because each emirate has its own prefix. Moving the numbers to a cloud phone system is one way to separate the number from the building.
In most moves it is the business internet connection at the new address, together with the decision on how your phone numbers move. Carriers do not publish a fixed lead time for a new business fibre connection, and it depends on whether the building is already served. Order it as soon as the lease is agreed.
Cat 6A gives you more headroom for faster connections and powered devices such as access points and cameras, and it is the safer choice for a fit-out you expect to keep for years. Cat 6 can be adequate for a short lease or light use. Whichever you choose, insist on certification test results for every link and a labelling scheme you can read later.
In Dubai, selling and installing security systems is a licensed activity under Law No. 12 of 2016, overseen by SIRA. Use a provider licensed by SIRA, and ask them which requirements apply to your type of premises before the design is fixed. Building management may also have its own rules for cameras in shared areas.
Take a full backup and prove it restores before anything is unplugged, and keep at least one copy away from both the old and the new office. Sync users' desktops and documents to cloud storage so a damaged laptop does not mean lost work. Move servers last and have a written plan for switching back if something fails.
NETON delivers structured cabling, IT infrastructure, business phone systems, CCTV and security systems, audio-video and IT support for projects in the UAE. That covers each workstream in this checklist under one point of contact. Get in touch with your move date and new address to plan the sequence.